Monday, April 26, 2010

Replacing Entrance Concrete

The missing concrete at the front entrance is put in place by the crew of Read Contracting Ltd.

Thursday, April 22, 2010

An Unusual View

"On a clear day you can see"....
On this clear day Camroseans could see this gigantic crane from miles away! It was on site to install the second roof top air handling unit that will service the auditorium and stage. This view was captured by David Roth, Bailey's architectural adviser, as it was raised up to the roof of the Bailey Theatre annex addition.

Tuesday, April 20, 2010

Preview of Marquee

Although a sneak preview, shown here is the new marquee currently being reconstructed by Blanchett Neon of Edmonton. The marquee is expected to be installed the last week of April, 2010.

Monday, April 19, 2010

Preparing Front Lobby

Dave Borgel removes the old floor of front lobby so that the new plywood sub-flooring can be installed.

Wednesday, April 7, 2010

Preping Atop


Workers apply the exterior air barrier and flashing upstairs on the Bailey in preparation for insulation and stucco.